PECO will be replacing a gas line on Chamounix Road starting on Monday, November 10, 2025. Please note the following:
- The duration of the project is 11/10/2025 – 12/11/2025, pending inclement weather
- Chamounix Road will be closed 24/7 from approximately 11/23/2025 to 12/01/2025
- There will be lane restrictions on Chamounix Road throughout the project duration
- The hours of work are 7:00 AM to 3:00 PM, except work hours will be extended during the road closure:11/23-12/01
- Follow the posted detour route
Questions regarding this project should be directed to William Morris of Miller Brothers at 610-832-1000.