RADNOR TRAIL EXTENSION (Website Update #1) February 2017

Next Study Committee Meeting: Wednesday, March 15, 2017 

February Work Update:

The initial site clearing to facilitate survey and evaluation of the PennDOT owned right of way (the former P&W rail right of way) east of Radnor-Chester Road, site of the trail extension, was completed in December by Kee Landscaping, Inc. Additionally, Gilmore & Assoc., Inc., consultant to Campbell Thomas & Co., completed the engineering field survey of the right-of-way in February and base survey plans are underway. The Campbell Thomas & Co. design team, including TPW Design Studios, Jeff Case, PE and RETTEW Assoc., Inc., are currently working on the right of way evaluation, schematic design of the trail extension, and schematic design of the proposed culvert which will create an underpass at Radnor-Chester Road. The present goal is to submit Preliminary Design documents to PennDOT by May of 2017.

Study Committee Update:

During our February Study Committee Meeting, three parking options for the trail extension were discussed. These parking options will be discussed with adjacent neighbors in the coming weeks as well as at the April 6th Public Workshop for the Radnor Trail Extension. 

Key Dates: 

1st Public Workshop -  Thursday April 6th (6:30pm) 
Radnor Township Building
301 Iven Ave., Radnor, PA 19087

Community Q&A


1) “Is there a map showing the new trail extension?”
- A map showing the Radnor Trail Extension has been posted to the website.  Click here For The Map

2) “What about Buffers and Fencing along the Trail?”
- Trail fencing and landscaping will be addressed in a landscaping plan later in the design process. Coordination with the impacted property owners along the trail extension will be part of the landscaping process.